| On the Operational Status in the Kashima Plant |
 |
| Mitsubishi Chemical Corporation |
 |
As for the operational status in the Kashima Plant as of December 25, 2007, we announce as follows:
| 1. |
Operational status |
| |
I. |
Shutdown at present |
| |
|
i
ii
iii
iv |
No.2 Ethylene
No.2 Benzene
Polyethylene A, Polyethylene B, Polyethylene C
Polypropylene B, Polypropylene C |
|
| |
|
|
| |
II. |
Operation reduction |
| |
|
i
ii
iii
iv |
Ethylene oxide and ethylene glycol:
Ethyl benzene:
Cumene:
Phenol: |
60% production
60% production
60% production
60% production |
|
| |
|
|
| 2. |
Delivery
As for received purchase orders, products to be delivered by the end of this year have been all set as originally scheduled. |
|
|
 |
 |
|
 |
 |